# Cumberland commissioners advance courthouse security contract, plan Dec. 14 hearing to extend data center moratorium
- URL: https://www.ccnc.news/cumberland-commissioners-advance-courthouse-security-contract-plan-dec-14-hearing-to-extend-data-center-moratorium/
- Published: 2026-11-20T18:36:39.000Z
- Updated: 2026-11-20T18:36:39.000Z
- Author: CCNC News Staff
- Tags: Government, Cumberland County

FAYETTEVILLE — The Cumberland County Board of Commissioners, meeting in its monthly agenda session Thursday, Nov. 12, sent a courthouse security contract and several policy changes toward its Nov. 16 regular meeting, agreed to hold a special meeting Dec. 14 on extending the county's data center moratorium, and asked staff to come back in December on requests from the Town of Spring Lake and the county's district court judges.

Agenda sessions are where the board discusses items and, in most cases, votes to place them on the consent agenda of an upcoming regular meeting for final approval.

## Courthouse security

On a 4-2 vote, commissioners agreed to place on the Nov. 16 consent agenda the scope of work for a professional security services contract with Universal Protection Service LLC, not to exceed $821,658.40, with Chairman Kirk deViere authorized to sign once the contract passes legal review and pre-audit. Commissioner Henry Tyson's motion added a condition that the contract would not begin until after a 120-day period so that sworn officers can be in place. Tyson, deViere, Commissioner Pavan Patel and Commissioner Marshall Faircloth voted in favor. Vice Chairwoman Veronica Jones and Commissioner Glenn Adams voted no.

Assistant County Manager Faith Phillips said the board allocated $822,127 for expanded courthouse security in July. The proposed staffing model calls for four sworn officers and four unarmed security guards at three posts plus a roving officer, with the guards handling metal detectors, visitor screening and entrance access control. She said the company told staff it takes about 120 days to recruit, onboard and certify sworn company police officers, and that Sheriff Johnathan Morgan had raised concerns about deputies working side by side with contracted personnel and about a December start during the sheriff's office transition.

Adams said he did not understand why the county would put unarmed people at the doors. "It should start with sworn officers," he said. Morgan, who is retiring, told the board the sheriff's office would support whatever the board decided and called his current approach of moving deputies around the courthouse "a short-term solution for a long-term problem." Jones said she could not support the contract when it would not take effect until after a new sheriff takes office, and that the incoming sheriff should have a say.

## Data center moratorium

County Attorney Rick Moorefield said the county's data center moratorium expires Dec. 15 and a zoning ordinance amendment will not be ready by then. He asked to advertise a public hearing on extending the moratorium for another six months. After discussing several dates, the board reached consensus on a special meeting at 6 p.m. Monday, Dec. 14, for the hearing. Adams said six months was too long and suggested about four. Moorefield said the extension would run until an ordinance is adopted, up to six months. Moorefield said before the meeting ended that he was checking a statute on whether the hearing must be held at a regular meeting. A presentation on the draft data center ordinance is scheduled for the Nov. 16 meeting.

## Legislative agendas

Diane Rice, the county's chief innovation and strategy officer, presented draft state and federal legislative agendas ahead of a Dec. 10 meeting with the county's legislative delegation. The state draft includes $100 million for water and sewer infrastructure, restoration of $30 million in statewide viable utility reserve funding, $40 million for school construction, recognition of 911 telecommunicators as first responders and preserving local zoning authority, including the ability to set standards for data centers.

A motion by Faircloth to approve the agendas as a draft subject to further review failed 2-3, with deViere and Faircloth in favor and Tyson, Jones and Patel opposed, after Faircloth declined Tyson's proposed amendment requiring a public hearing. The board then approved, 4-1, Tyson's motion to receive the drafts subject to revisions and to hold a public hearing after talks with the delegation and before formal approval. Faircloth voted no. Adams had not yet arrived; the chairman said at the start of the meeting that Adams was coming from a Fayetteville State University trustees meeting. Jones also asked that the drafts be sent to the county's appointed boards for comment.

## Spring Lake requests

County Manager Clarence Grier said the Town of Spring Lake asked the county for $840,854 toward a $1,340,854 construction contribution for a Piedmont Natural Gas line extension into Spring Lake, with the town putting up $500,000\. Moorefield said the only statutory authority he had found for the county to participate in a natural gas extension is for a specified industrial site, "and that's not what this is." Commissioners voiced support for the project and reached consensus to have the manager and attorney return in December with a funding source and a legal mechanism.

The board also discussed a proposed county lease of the Spring Lake Recreation Center as an asset of the county recreation district. Moorefield said the draft lease in the agenda packet was prepared hurriedly and was not one the county would use, and that any lease must make the center available to all district residents. The town's resolution asks for $131,249 a year; Grier said the amount relates to the town's debt on the center, which runs to 2047\. The board directed Moorefield to draft a lease, work it out with the town and bring it back at the December agenda session with an update on the building's deferred maintenance.

## Specialty courts

Assistant County Manager Heather Skeens said the county received an Oct. 19 letter from the district court judges asking that the county's Justice Services department no longer oversee the treatment courts, while the coordinators remain county employees and the county continues to administer grant funds. Staff recommended ending the county's involvement as grants expire and asked that the item go on the Nov. 16 consent agenda. Tyson and Jones said they favored accommodating the judges. The board did not vote; deViere said staff will bring back several options in December, including staff's recommendation, the judges' request and a county-funded model raised by Jones.

## Other actions

## The board voted unanimously to:

\- Place on the Nov. 16 consent agenda revised Change Order No. 2 to the Gray's Creek Phase 1 test well contract with Bill's Well Drilling Co., keeping the not-to-exceed amount at $775,996 and extending substantial completion to Oct. 2, 2027, and final completion to Dec. 31, 2027, to allow for one more test well at a location not yet chosen. 

\- Approve Change Order No. 1 to the Gray's Creek Phase 1 water distribution contract with Jymco Construction Co., extending substantial completion to March 24, 2027, and final completion to April 23, 2027, with no change to the $5,927,429 contract amount. 

\- Approve changes to the attendance policy for county boards and commissions. The changes drop special events from the attendance requirement, count excused absences as attendance, and have the clerk send a member a letter before removal, with 30 calendar days to respond. 

\- Place updated Board of Commissioners Rules of Procedure on the Nov. 16 consent agenda. 

\- Place on the Nov. 16 consent agenda amendments to the county's conflict-of-interest policy, which Assistant County Manager Deborah Shaw said were requested by the N.C. Department of Environmental Quality after a grant monitoring review.

On a 4-2 vote, with Jones and Adams opposed, the board placed a new committee flow policy, which sets how items and commissioner requests move through board committees, on the Nov. 16 consent agenda.

The board also voted on Patel's motion to terminate the county's repurchase right on SkyREM LLC's land at the Cedar Creek Industrial Park and record a release, placing it on the Nov. 16 agenda. No opposition was announced. Robert Van Geons, CEO of the Fayetteville Cumberland Economic Development Corp., said SkyREM bought the remaining park land in 2021 and did not build within the agreement's timeline, that about 66% of the land is not buildable, and that the clawback would make it hard for a company that wants to build there to move forward.

## Unhoused support center

Skeens told the board that staff is not recommending the lone response to a request for proposals for a temporary emergency shelter, which proposed using a hotel at a cost of just over $2 million for a year. Staff also is not recommending either of two responses from potential development partners. She said three schools the Board of Education voted to sell to the county for $1 each, Manchester Elementary, Algernon Wilkins and Lillian Black, need at least $8 million in repairs combined and would most likely have to be demolished for the center. She said the City of Fayetteville's special use permit process for the Hawley Lane site would take about 60 days, and that the county is still waiting on the school board. The earliest opening with a new building is now March 2028, she said. Commissioners asked to see the proposals and discussed reopening the solicitations, and held further discussion for closed session.

## Other business

\- FCEDC's Van Geons reported limited developer interest in a standalone full-service hotel on the county's Gillespie Street property and recommended marketing the full site for broader mixed-use redevelopment. - Skeens said the county, Alliance Health and Cape Fear Valley Health are working toward a December 2027 transition of behavioral health crisis services at the county-owned Roxie building. Tyson asked for monthly updates at agenda sessions. - The board reached consensus to have staff review Commissioner Tyson's requests for a Lenco BombCat bomb squad vehicle and a drone-as-first-responder program and report back within 60 days, including possible grants. Tyson's proposal for a 13-member county public safety commission will return in December after commissioners give feedback. Jones disagreed with that direction. - Morgan, at the start of the meeting, thanked commissioners for their support during his time as sheriff. Commissioners thanked him for his service, and deViere had his remarks entered into the minutes.

The board ended its open session by going into closed session for an honorary award, attorney-client matters, property acquisition and economic development.

Video of the meeting: [https://www.youtube.com/watch?v=kkuT2VFds74](https://www.youtube.com/watch?v=kkuT2VFds74&ref=ccnc.news)